Open-book cost-plus: how we charge

We do not give fixed quotes. We estimate the work, then charge what it actually costs plus a margin of 15%, and you see every hour worked and every invoice paid.

Why we do not give fixed quotes

The first question we are usually asked is whether we can quote for a job, because people want to know whether the work fits their budget. We do not give fixed quotes. We do not believe quotes and competitive tenders give the price certainty a client needs to budget accurately.

An old building almost always holds surprises. It may be rotten timbers behind plaster, a wall with no foundation, or an earlier fireplace that the conservation officer wants kept. A fixed price either leaves these out, so they come back later as extras, or it includes an allowance for them that you pay whether or not they happen.

How it works

  • We estimate the works, using our experience to allow for the changes and extras an old building is likely to bring.
  • Work can start as soon as the drawings and consents are in place, without the cost and delay of a tender.
  • At each valuation we charge for the labour, materials and subcontracted work actually used, at cost, plus our 15% margin.
  • We update the budget at every valuation, so the cost of the work and the budget stay in step.
  • Because changes show up as they happen, there is no bill for unexpected extras at the end.

What you pay

Labour is charged at agreed rates. Materials and subcontracted work are charged at the price we paid. Our margin of 15% is added to that cost, then VAT and any retention the contract sets. The margin covers our fixed overheads and our profit.

How a valuation adds upIllustrative figures
Labour£12,360
Materials and subcontractors£8,140
Cost of the works£20,500
Our margin at 15%£3,075
Net total£23,575
VAT at 20%£4,715
Due this valuation£28,290

We have long-standing accounts with our suppliers and good credit references, so we buy materials and subcontracted work at competitive rates. We pass all of the savings on to you, with a copy of every receipt and invoice. We believe you cannot improve on an open-book cost if the builders are good and hard working, the job is well managed, and the materials are well sourced.

What you see at each valuation

We built our own system, WCR Valuations, to run open-book costing properly. It turns our timesheets and supplier invoices into a clear payment application, and records every change made along the way.

Each valuation we issue comes with a secure link. Open it on your phone or computer, with no account or password to set up.

Valuation 7

Example project: kitchen and rear extension

Issued
Labour£12,360.00
Suppliers, 46 invoice lines£8,140.00
Overheads and profit, 15%£3,075.00
VAT£4,715.00
Not charged, 6 hours (shown, not in the total)£0.00
Balance due£28,290.00
An example valuation. The figures are illustrative.
  • Summary

    Labour, materials, our margin, any retention and VAT, down to the balance due. It works as the invoice.

  • Timesheets

    Every hour worked on your job, by person and by part of the job.

  • Suppliers

    Every supplier invoice line, with credit notes applied. You also receive a copy of each receipt and invoice.

  • History

    How the cost has built up across every valuation so far.

  • Who worked on the job

    Each tradesman and how long they spent on your job, valuation by valuation.

  • PDF, print or spreadsheet

    Take the figures away for your own records, your accountant or your lender.

Where different rates of VAT apply to different parts of the work, each part is shown at its own rate.

Why you can rely on the figures

  • Once a valuation is issued it is locked. The figures cannot be changed afterwards.
  • Labour is charged at the rates in force when the valuation is issued, and those rates are fixed for that valuation.
  • Time that is disputed or not chargeable stays visible on the valuation, marked as not charged, and is left out of the total.
  • Every correction and change of rate is recorded. Nothing is quietly rewritten.

Is cost-plus right for your project?

It suits old and listed buildings, where nobody can know everything before work starts. The final cost depends on the work actually done. If opening up reveals more, the budget changes, but you see it at the next valuation, with the reasons, rather than at the end.

It also suits clients who want to make decisions as the job goes on, such as changing a finish or adding work, because each change is priced at cost rather than as a variation to a fixed contract.

Is cost-plus more expensive than a fixed price?

We do not believe so. A fixed price has to include an allowance for risk, which you pay whether or not the risk arises. With cost-plus you pay for what happens, plus 15%, and you can see what that is.

Can we still have a budget?

Yes. Every job starts with an estimate, and the budget is updated at each valuation so you always know where it stands.

Can we check the invoices?

Yes. Every valuation lists each supplier invoice, and you receive a copy of every receipt and invoice.

To talk about your project, call Geoffrey on +44 7740 471 543 or send us the details.